BCT 143 week 4 Fri/Sat

Image
On Saturday I started a Christmas project for my girlfriends 2 year old daughter. It will be an 8x5 tiny house with two floors.  The first floor was constructed with wood we got from pallets at the mill.  The boards are 1x5 and the post and 3x4.  Because it' is going to be a small structure and the post are so big we went 24" o.c

BCT 143 week 4 wednesday (Maybe Week 7)

Image
The 3rd wall is being built right on the floor system.  to prevent the wood from splitting, holes are pre drilled into the plates and then using a 3 inch screw, connected to the wall stud. The 3rd wall is being erected in the picture above.  while trying to line up the walls on to the pre laid out marks, we are ensuring the the wall will be flush with the 2 that were previously put up.

BCT 143 week 2 friday (Maybe Week 6)

Image
In the first picture you can see our chalk line is done again on the floor system to make sure we are still squared and to also give us line for our wall to sit on.  the line has to be within 3 1/2" inches from the end to make sure the sheathing for the wall will be flush with the whole entire system. The second picture shows the wall in progress.  the studs are placed 16" OC from the end and is almost ready for sheathing.  first the wall must be secured to the floor system before sheathing can be applied.  this helps the wall stay squared while hammering in nails.

BCT 143 week 2 wednesday (Week 5 or 6?)

Image
The first picture shows the group flipping the floor system over so the sheeting can be applied to the floor.  you can also see in the picture the 4x4 skids attached to the floor that will help with moving the shed and prevent damage to the floor. The second picture is the finished product of the floor system.  you can see the sheathings are tongue and grove which are self spaced.  There seems are also off set.  one sheet was a full 8' piece that was glued and nailed to the floor. The second piece is measured from the end of the previous sheet till about 1/2" from the box.

BCT 143 week 1 Friday (Maybe Week 4)

Image
In the first picture you can see our chalk line was put onto the floor system in preparation for the floor sheathing.  we marked the line 4 feet from the end where the two sheets will connect. The second picture on the bottom is the blocking that we installed that will go bellow the 4x4 skids.  Blocking will help secure the skids to the floor system.  the skids themselves which are not pictured above are used to to create space for something to pick up the shed once built.  They also prevent damage to the floor while moving it around.

BCT week 3 monday

Image
On Monday I got to work on the stair well opening in my floor section.  I started out by laying the full length inside joist so that I would be able to through nail them into the outside header.  I then through nailed the outside header into the tail joist and then applied the inside header.  It is not pictured above but 2 more full length joist were added to the opening on the outside to give it more strength.

BCT week 2

Image
During week 2 a few of us spent time working on finishing the roof.  myself and one other student worked on getting the drip edge finished.